RFP 44-28-75-04-P Swing Bridge Replacement - The Engineer
The Government of Bermuda is seeking a suitably qualified and experienced engineering firm to act as The Engineer to deliver the Swing Bridge Replacement Project in St. George’s Parish, Bermuda. The new bridge will be a seven-span viaduct, comprised of steel box girders, supported by reinforced concrete abutments and piers, formed on reinforced concrete pile caps seated on tubular piles. The viaduct includes a 30.1m lift span actuated with large hydraulic cylinders.
This request for proposals is for the role of The Engineer, to administer the project using the 1999 FIDIC Conditions of Contract for PLANT and Design-Build (yellow book).
RFP Contact and Registration of Interest
Interested parties that require any additional information may contact :
Attention: Austin Kenny, Principal Structural Engineer - Email: avkenny@gov.bm
** Absolutely no verbal questions/clarification will be acknowledged.
Key Dates
| Issue Date of RFP | Wednesday April 15, 2026 |
| Registration Opening Date | Wednesday April 15, 2026 |
| Release of Works Information Package to Registered Proponents | Thursday April 16, 2026 03:00:00 PM |
| Pre-Bid Conference Call | Wednesday April 29, 2026 11:00 AM |
| Registration Closing Date | Wednesday May 27, 2026 03:00:00 PM |
| Deadline for Questions | Wednesday June 03, 2026 |
| Deadline for Issuing Addenda | Wednesday June 24, 2026 |
| Submission Deadline | Wednesday July 08, 2026 03:00:00 PM |
| Rectification Period | 5 business days |
| Anticipated Ranking of Proponents | Wednesday July 29, 2026 03:00:00 PM |
| Contract Negotiation Period | 28 calendar days |
| Anticipated Execution of Agreement | Wednesday October 07, 2026 03:00:00 PM |
*Late submission will not be considered.